Technical Analysis
Made-in-Italy tracker: now a great deal on price, too.
📅 August 2026
⏱ Reading time: 6 minutes

PVclick Strategy Team
Operational and commercial analysis for the Italian PV sector
What you will find in this article
- What changes from July 1, 2026, with the new EU steel safeguard measure
- How the CBAM imposes costs and red tape on every imported structure
- Why the "melt and pour" rule closes the triangulation loophole
- The concrete step to protect the margins on your ground-mounted projects
The list price has stopped telling you the truth.
For years, the choice of structure for a ground-mounted system was almost automatic: three quotes would be requested, the Asian tracker with the lowest list price would win, and the cost difference compared to a European manufacturer easily covered transport and customs clearance. In 2026, two European measures shifted the balance, and both directly affect the raw material used to make trackers: steel.
The first is the new EU steel safeguard measure, effective from July 1, 2026: duty-free import quotas are dropping to 18.3 million tonnes per year—a 47% decrease compared to 2024—and the duty on volumes exceeding this threshold is doubling from 25% to 50%. The second is the definitive phase of the CBAM (Carbon Border Adjustment Mechanism, the European system that imposes a charge on the embedded carbon in imports), which becomes operational on January 1, 2026, specifically covering steel, iron, and metal structures.
Where the surcharge is hidden
1. Out-of-quota duty: from 25% to 50%
Duty-free quotas are exhausted on a product-family and quarterly basis; once the quota is filled, a 50% duty applies to every subsequent tonne. For those ordering structures months in advance, the primary issue is uncertainty: at the time of ordering, you do not know whether your shipment will clear customs within or outside the quota. For a multi-MW supply, the difference between the two scenarios is worth more than any discount negotiated with the manufacturer.
2. The CBAM: certificates, reporting, and consultants
3. "Melt and pour": triangulation no longer works
The classic workaround—routing steel through or reprocessing it in a third country to alter its country of origin—has been eliminated: as of October 1, 2026, the “melt and pour” rule applies, meaning that for tariff purposes, the country where the steel was melted and cast determines its origin, not the country where it was bent or assembled. To European customs authorities, a “Vietnamese” product made from steel melted in China remains Chinese steel.
4. The risk you never budget for
Beyond the known costs, there are potential ones: customs holds due to incomplete CBAM documentation, disputes regarding origin, and delivery delays that eat into the penalties outlined in your EPC (Engineering, Procurement, and Construction—i.e., turnkey) contract. If your construction schedule hinges on a ship and three customs clearance stages, you are essentially paying for that low list price with added risk.
📊 The big picture in a single sentence:
In 2026, the proper comparison between trackers will be based on the final price delivered to the project site—including customs clearance, CBAM certificates, compliance costs, and delay risk. On this basis, the European product—and the Italian one in particular—becomes competitive again across a much wider range of projects than before.

The Italian alternative: TATM3
PVclick has added the TATM3 to its catalog—a horizontal single-axis tracker designed and manufactured entirely in Italy by a metalworking company with 64 years of experience and 240 MW of ground-mounted installations to its name. No shipping containers, no quotas to track, and no CBAM paperwork: the steel is smelted and processed in Europe, and the price you sign for is the price you pay.
Technically speaking, this is a 1P tracker featuring ±55° rotation, uniform-distribution backtracking, and wind and snow sensors with automatic safety positioning; it has undergone wind tunnel testing using full-scale panels and complies with CEI EN 62817 standards, including testing against extreme winds of 40 m/s. According to the manufacturer, on-site assembly requires up to 40% fewer man-hours compared to other single-axis systems, and direct support is available within 24 hours for both mechanical and electronic components. You can find full specifications and technical data on the TATM3 tracker page.
The logic is the same as when you import modules directly from the factory: shortening the supply chain and eliminating middlemen. For modules, the short supply chain runs through China, as tariffs and CBAM do not currently affect panels from there; for steel structures, however, the shortest and most cost-effective supply chain in 2026 is one that originates in an Italian factory. A sound purchasing strategy combines both approaches:
The three moves to make now
- Recalculate the offers on the table: ask each non-EU supplier for the final price—including customs clearance, duties, CBAM, and compliance costs—and clarify who bears the cost if the shipment exceeds the quota.
- Verify the “melt and pour” origin of the steel for every tracker in the tender: as of October 1, 2026, this is the factor that determines the duty, not the country of assembly.
- Include at least one European tracker in the tender: when comparing cleared prices and guaranteed delivery times, the outcome is no longer a foregone conclusion in 2026.
Anyone buying structures based solely on list prices is using a pricing playbook for a market that no longer exists. Those who compare cleared prices make decisions based on real figures—and today, those figures increasingly speak Italian.
How much does your next tracker camp really cost?
Send us the layout or dimensions of your ground-mounted project to receive a TATM3 quote on a delivered-to-site basis, allowing you to compare it item-by-item with offers from outside the EU.